Mermaid Gantt chart examples
Updated
A Mermaid Gantt chart starts with the gantt keyword, an optional title and a dateFormat, then one line per task: the task name, a colon, and comma-separated metadata such as tags, an ID, a start date or after another task, and a duration. Sections group the rows. Every example below is rendered live from its code.
Basic Gantt chart
The smallest useful chart: dateFormat tells Mermaid how to read your dates, section starts a group of rows, and each task gives a start date and a duration. A task with only a duration starts where the task on the line above it ends.
gantt
title Website relaunch
dateFormat YYYY-MM-DD
section Design
Wireframes :2026-01-05, 4d
Visual design :5d
section Build
Front end :8d
Content migration :4d
section Launch
QA and fixes :3dDependencies with after and until
Give a task an ID and later tasks can start after it. List several IDs and the task waits for the last of them to finish. until ends a task when another one starts; it needs Mermaid 10.9.0 or later. axisFormat %b %d keeps the dates on the axis short.
gantt
title Mobile app release
dateFormat YYYY-MM-DD
axisFormat %b %d
section Backend
API design :api, 2026-02-02, 5d
API build :build, after api, 10d
section Apps
iOS screens :ios, 2026-02-02, 12d
Android screens :android, 2026-02-04, 12d
Integrate API :integrate, after build ios android, 4d
section Release
Beta testing :beta, after integrate, until launch
Store launch :milestone, launch, 2026-03-09, 0dDone, active and critical tasks
Tags change how a bar is drawn: done for finished work, active for work in progress and crit for the critical path. Tags go first in the metadata, before the ID, and crit combines with either of the other two.
gantt
title Sprint 14
dateFormat YYYY-MM-DD
section Stories
Rate-limit login :done, s1, 2026-03-02, 3d
Password reset email :active, s2, after s1, 3d
Audit log export :s3, after s2, 4d
section Release blockers
Security review :crit, done, r1, 2026-03-02, 2d
Pen-test fixes :crit, active, r2, after r1, 4d
Release sign-off :crit, r3, after r2, 1dMilestones
Add the milestone tag and a zero duration to mark a single moment such as a deadline or a launch. Mermaid places the marker at the start date plus half the duration, so 0d puts it exactly on the date. A chart made only of milestones, with a section per phase, is a timeline-style Gantt: one marker per event on a real date axis and no bars at all.
gantt
title Release timeline (milestones only)
dateFormat YYYY-MM-DD
axisFormat %b %d
section Discovery
Kickoff :milestone, m1, 2026-01-12, 0d
Research complete :milestone, m2, 2026-02-02, 0d
section Build
Alpha :milestone, m3, 2026-03-02, 0d
Beta :milestone, m4, 2026-04-06, 0d
section Launch
General availability :milestone, m5, 2026-05-04, 0d
Retrospective :milestone, m6, 2026-05-18, 0dExclude weekends and holidays
excludes weekends skips Saturdays and Sundays, and dates in your dateFormat add single days such as a public holiday. Mermaid does not cut a gap into a bar: it extends the task by the excluded days, so 4d still means four working days.
gantt
title Onboarding plan (working days only)
dateFormat YYYY-MM-DD
excludes weekends 2026-05-25
section Week one
Laptop and accounts :a1, 2026-05-20, 2d
Codebase walkthrough :a2, after a1, 3d
section First ticket
Small bug fix :a3, after a2, 4d
Code review and ship :a4, after a3, 2dAxis labels and weekly ticks
axisFormat sets the dates printed under the chart using d3 format codes, here %b %d for "Jan 05". tickInterval (Mermaid 10.3.0+) fixes the spacing of the ticks, and weekday monday starts weekly ticks on Monday instead of Sunday.
gantt
title Q1 roadmap
dateFormat YYYY-MM-DD
axisFormat %b %d
tickInterval 1week
weekday monday
section Platform
Billing v2 :2026-01-05, 4w
Usage dashboards :3w
section Growth
Referral program :2026-01-12, 5w
Pricing page test :2wA schedule in hours and minutes
Gantt charts also work within a single day: set dateFormat HH:mm, give durations in m or h, and print times on the axis with %H:%M. todayMarker off hides the vertical line Mermaid draws at the current date and time.
gantt
title Release day runbook
dateFormat HH:mm
axisFormat %H:%M
todayMarker off
section Prepare
Freeze main branch :09:00, 30m
Build and sign :45m
section Deploy
Canary rollout :crit, 60m
Full rollout :crit, 90m
section Verify
Smoke tests :30m
All clear :milestone, 0mRoadmap with a styled today marker
The today marker is a vertical line at the current date, drawn only while today falls inside the chart. Put CSS properties after todayMarker to restyle it; axisFormat %b %Y labels a long roadmap by month.
gantt
title Product roadmap
dateFormat YYYY-MM-DD
axisFormat %b %Y
todayMarker stroke-width:4px,stroke:#4f46e5,opacity:0.6
section Product
Editor rewrite :done, 2026-06-01, 120d
Team workspaces :active, 2026-09-15, 150d
Offline mode :2027-02-01, 90d
section Infrastructure
Database migration :done, 2026-07-01, 60d
Multi-region hosting :2026-10-01, 180dHow does Mermaid work out the dates of a task?
Every task line is a name, a colon, and metadata separated by commas. Tags come first if you use any (done, active, crit, milestone). What remains is read by position: one item is the end, given as a date or a duration, and the task starts where the previous line ended; two items are a start and an end; three items are an ID, a start and an end. The start can be a date in your dateFormat or after one or more task IDs, and the end can be a date, a duration, or until another task.
Durations are a number and a unit: ms, s, m (minutes), h, d, w, M (months) or y, and decimals such as 1.5d are allowed. Mermaid’s documentation warns that an invalid token such as 3dX is ignored and the task gets zero duration, so a typo shows up as a missing bar rather than an error.
| Metadata after the colon | Start | End |
|---|---|---|
2026-01-05, 5d | The date given | Start plus 5 days |
5d | End of the task on the line above | Start plus 5 days |
2026-01-05, 2026-01-09 | The first date | The second date |
id1, after a b, 4d | The latest end of tasks a and b | Start plus 4 days |
id2, 2026-01-05, until c | The date given | Start of task c (Mermaid 10.9.0+) |
milestone, m1, 2026-03-09, 0d | The date given | A single point: a milestone |
What is the difference between dateFormat and axisFormat?
dateFormat is how Mermaid reads the dates you type. It uses Day.js tokens and defaults to YYYY-MM-DD. axisFormat is how Mermaid prints dates on the axis. It uses d3 time-format codes, which start with a percent sign, and also defaults to a year-month-day layout. The two are independent: you can type ISO dates and print Jan 05, or type times with HH:mm and print %H:%M, as in the runbook example.
| Token | Used in | Meaning |
|---|---|---|
YYYY, MM, DD | dateFormat | Four-digit year, month number, day of month |
HH:mm | dateFormat | 24-hour time |
X | dateFormat | Unix timestamp in seconds |
%Y, %m, %d | axisFormat | Year, zero-padded month, zero-padded day |
%b, %B | axisFormat | Abbreviated or full month name |
%a | axisFormat | Abbreviated weekday name |
%H:%M | axisFormat | Hours and minutes, 24-hour clock |
%W | axisFormat | Week number of the year, weeks starting on Monday |
Which other Gantt options does Mermaid have?
These are the remaining Gantt keywords and settings from Mermaid’s documentation, with the version that introduced the newer ones. Keywords go on their own line after gantt; displayMode and topAxis go in a config block at the top of the diagram, under gantt.
| Option | What it does |
|---|---|
weekend friday | With excludes weekends, treats Friday and Saturday as the weekend (Mermaid 11.0.0+) |
Several excludes lines | Splits a long list of excluded dates across lines (Mermaid 11.16.0+) |
tickInterval 1day | Fixed tick spacing: a number plus millisecond, second, minute, hour, day, week or month (10.3.0+) |
vert tag | Draws a vertical marker line at a date without taking up a row (Mermaid 11.7.0+) |
displayMode: compact | Puts several tasks of a section on the same row when they do not overlap |
topAxis: true | Adds the date labels above the chart as well |
click id href "url" | Turns a task into a link, only where the page renders Mermaid with securityLevel set to loose |
%% comment | A line starting with two percent signs is ignored |
Why is my Mermaid Gantt chart not rendering?
Start with the metadata order. Tags must come before the ID: done, t1, 2026-05-18, 3d works, while t1, done, 2026-05-18, 3d makes the whole diagram fail. A task name cannot contain a colon, because the first colon starts the metadata. Every section needs a name; a bare section line breaks the drawing. And excludes accepts dates, weekday names and weekends, but not weekdays.
Some mistakes do not raise an error at all. A date typed in a different layout from your dateFormat, or an after that names an ID that does not exist, can still render, with the bar somewhere you did not expect. If a bar is missing or misplaced, check the IDs and the date layout first. Finally, check the renderer’s version: until needs 10.9.0, weekend 11.0.0, vert 11.7.0 and several excludes lines 11.16.0, and a platform on an older Mermaid will reject or ignore them.
Should you use a Gantt chart or a timeline?
Use a Gantt chart when dates, durations and dependencies matter: a project plan, a release schedule, a sprint. Use Mermaid’s timeline when you only need the order of events grouped by period, such as a product history, because it needs no dates or durations at all. A Gantt chart made only of milestones, as in the Milestones example above, sits between the two: it keeps the one-marker-per-event look of a timeline but spaces the events by their real dates. To show how a total splits into parts rather than how work is scheduled, a pie chart is the better fit.
How do you make one task start after another in a Mermaid Gantt chart?
Give the first task an ID, the first item after any tags, as in Design :des, 2026-01-05, 5d. Then start the next task with after des, as in Build :after des, 10d. A task can wait for several tasks at once, after des api, and then starts when the last of them ends. A task with no start at all begins where the task on the line above ends, which is often all you need.
How do you exclude weekends and holidays in a Mermaid Gantt chart?
Add excludes weekends after dateFormat, and add specific dates to the same line, written in your dateFormat, for holidays. Excluded days are shaded on the chart and do not count towards durations, so a task that crosses a weekend gets longer instead of losing days. From Mermaid 11.0.0, weekend friday makes Friday and Saturday the weekend.
Does Mermaid mark tasks as done automatically?
No. done and active are tags you write yourself; Mermaid does not compare them with today’s date. What it does draw automatically is the today marker, a vertical line at the current date whenever today falls inside the chart. You can restyle that line with todayMarker followed by CSS properties or hide it with todayMarker off, but updating task status stays a manual edit.
Can a Gantt chart work as a timeline?
Yes, when the events have real dates. Give every row the milestone tag and a 0d duration and use a section per phase, as in the Milestones example above: Mermaid draws one marker per event on a date axis and no bars, so two launches a week apart sit close together and a six-month gap shows as a gap. For events without dates, such as eras or numbered steps, use Mermaid’s timeline diagram instead: it needs no dateFormat, gives every period the same width and lists several events under one period with extra colons.
Does GitHub render Mermaid Gantt charts?
Yes. GitHub renders fenced mermaid blocks in Markdown files, issues, pull requests, discussions and wikis with the Mermaid library, so the Gantt syntax on this page works there. GitHub chooses which Mermaid version it runs, so newer options such as several excludes lines may not work there yet. Its documentation suggests a one-word info diagram to show the version in use. See how Mermaid works in Markdown.
Can a Mermaid Gantt task link to a web page?
Yes, with a click line such as click t1 href "https://example.com", where t1 is the task ID. Mermaid only activates links and callbacks when the page renders diagrams with securityLevel set to loose; with strict they are ignored. Docs MD renders with strict, so a click line here is skipped without breaking the rest of the chart.